·Problem: The pole vibrates under the airflow generated by large vehicles passing by at high speeds.
Solution: Increase the foundation depth of the uprights and enlarge the flange size, or select octagonal or polygonal tubing with higher torsional stiffness.
·Problem: Rust at bolt connections.
Solution: All fasteners must be made of hot-dip galvanized or stainless steel. After installation, apply anti-rust grease or install plastic anti-rust caps.
·Important Notes: The excavation and pouring of the foundation pit must be customized according to the size of the signboard. After pouring, the signboard must be cured to the specified strength (generally 7-14 days) before hoisting the crossarm and signboard. Unauthorized construction is strictly prohibited.